On the afternoon of May 15th, the company had the labor competition mobilization meeting of CJ50’s launching with the theme “60 days’ hard work to ensure the launching”.
At the meeting, company read the implementation of the labor competition program, CJ50 project team, outfitting department, painting company gave the statement.
At present, there are two months left for the launching period, and CJ50-01 has the work including power system commissioning, lifting system commissioning, ballast tank tightness, painting and so on. The company has decomposed the construction plan, clarified the time node and the execution unit, and set up the labor competition leading group to hold the project promotion meeting on a regular basis every week, and to carry out the inspection and supervision on the development of the activities.